⏳ Final hours! Save up to 60% OFF InvestingProCLAIM SALE

Earnings call: IAMGOLD's Q2 results show positive ramp-up and cash flow

Published 09/08/2024, 21:50
© Reuters.
IAG
-

IAMGOLD (NYSE:IAG) Corporation (IMG) reported its second quarter 2024 operating and financial results, highlighting the successful ramp-up of its Cote Gold mine and the improved production and cash flow at its Essakane and Westwood mines. President and CEO Renaud Adams emphasized the company's strengthening financial position and the contribution of the Cote Gold mine to higher production and lower costs in the near future. IAMGOLD ended the quarter with strong liquidity and a solid balance sheet, with cash and cash equivalents of $511.4 million and total liquidity of approximately $915.7 million.

Key Takeaways

  • IAMGOLD's total gold production reached 166,000 ounces in Q2.
  • Production guidance for Essakane and Westwood mines increased, while cost estimates decreased.
  • Cote Gold mine achieved commercial production within four months of the initial gold pour.
  • The company reported positive mine site free cash flow: Westwood generated nearly $22 million and Essakane $118.2 million.
  • Capital expenditures were $92.6 million for Q2, with a total of $288.9 million year-to-date.
  • IAMGOLD revised its production guidance for Essakane and Westwood, with increased output expected.
  • The company plans a multi-day shutdown in September for optimization at Cote Gold mine.
  • IAMGOLD sees both Essakane and Westwood mines as valuable assets and is confident in their future performance.

Company Outlook

  • IAMGOLD expects significant improvement next year when Cote Gold is running at full capacity.
  • The company plans to address optimization issues at Cote Gold with a shutdown in September.
  • IAMGOLD is confident in the performance of its Essakane and Westwood mines and their future contributions to the portfolio.

Bearish Highlights

  • The company expects higher costs for waste stripping and operating costs.
  • There is a risk adjustment in the guidance due to potential disruptions in supply or power usage.

Bullish Highlights

  • Cote Gold is on track to ramp up to 90% of nameplate capacity by the end of the year.
  • IAMGOLD has updated the Gosselin mineral reserve and resources estimate, indicating robust potential.
  • The implementation of autonomous technology at Cote has been successful, improving operations and safety.

Misses

  • The company noted lower grades expected at the Essakane mine and a transition to lower grades in August.
  • There may be a loss in grade from the Grand Duc and no benefit from Fayolle at the Westwood mine.

Q&A Highlights

  • Discussion on the performance of autonomous operations at Cote and the positive grades at Westwood.
  • IAMGOLD sees potential for further optimization at Westwood, to be included in the upcoming 43-101 technical report.
  • The company is working to resolve dust control issues in their facilities, aiming for zero dust fugitive by September.

IAMGOLD Corporation, with its strong second quarter performance and strategic advancements in its mining operations, continues to build on its financial and production capabilities. The company's focus on ramping up its newest mine and improving existing operations positions it well for the future, as reflected in the positive outlook and confidence expressed by the CEO and the reported financial results.

InvestingPro Insights

IAMGOLD Corporation (IAG (LON:ICAG)) has shown a noteworthy performance, as evidenced by its latest financial results. With an eye on the company's future potential, let's delve into some insights provided by InvestingPro that could help investors understand the stock's current position and future prospects.

InvestingPro Data highlights that IAMGOLD has a market capitalization of $2.83 billion, which is indicative of its size and significance in the sector. The company's Price to Earnings (P/E) ratio stands at 16.38, suggesting that its shares might be trading at a reasonable valuation compared to its earnings. However, the adjusted P/E ratio for the last twelve months as of Q1 2024 is significantly higher at 40.02, which could imply expectations of future growth or a premium for the company's assets and market position. Importantly, the company's revenue growth was strong at 19.54% for the last twelve months as of Q1 2024, with an even more impressive quarterly revenue growth of 49.82% for Q1 2024, reflecting the successful ramp-up of operations and increased production.

InvestingPro Tips shed light on some strategic factors for investors to consider. Analysts are optimistic about IAMGOLD's sales growth in the current year, which aligns with the company's own positive outlook for its mines. Additionally, two analysts have revised their earnings estimates upwards for the upcoming period, signaling confidence in the company's earnings potential. These insights are particularly relevant as they corroborate the company's reported success in ramping up its Cote Gold mine and improving production at its other mines.

For those looking for more in-depth analysis, InvestingPro offers additional tips on IAMGOLD. Currently, there are 9 more InvestingPro Tips available, which could provide further guidance on the company's valuation, profitability, and stock performance trends.

To explore these insights in detail and to access the full range of InvestingPro Tips for IAMGOLD, interested readers can visit https://www.investing.com/pro/IAG. These tips could prove invaluable for investors seeking to make informed decisions about their investments in IAMGOLD Corporation.

Full transcript - Iamgold Corp (IAG) Q2 2024:

Operator: Thank you for standing by. This is the conference operator. Welcome to the IAMGOLD Second Quarter 2024 Operating and Financial Results Conference Call and Webcast. As a reminder, all participants are in listen-only mode and the conference is being recorded. After the presentation, there will be an opportunity to ask questions. [Operator Instructions] At this time, I'd like to turn the conference over to Graeme Jennings, VP, Investor Relations and Corporate Communications for IAMGOLD. Please go ahead, Mr. Jennings.

Graeme Jennings: Thank you, operator, and welcome everyone to the second quarter 2024 operating and financial results conference call. Joining me today on the call are Renaud Adams, President and Chief Executive Officer; Maarten Theunissen, Chief Financial Officer; Bruno Lemelin, Chief Operating Officer; and Tim Bradburn, Senior Vice President, General Counsel and Corporate Secretary. We are joining today from IAMGOLD's Toronto office, which is located on Treaty Treaty 13 territory on the traditional lands of many nations, including the Mississaugas of the Credit, the Anishnabeg, Chippewa, Haudenosaunee, and the Wendat peoples. At IAMGOLD, we believe respecting and upholding Indigenous rights is founded upon relationships that foster trust, transparency and mutual Please note that our remarks in this call will include forward-looking statements and refer to non-IFRS measures. We encourage you to refer to the cautionary statements and disclosures on non-IFRS measures, including the presentation and the reconciliations of these measures in our most recent MD&A, each under the heading, Non-GAAP Financial Measures. With respect to the technical information to be discussed, please refer to the information in the presentation under the heading, Qualified Person and Technical Information. The slides referenced on this call can be viewed on our website. I will now turn the call over to our President and CEO, Renaud Adams.

Renaud Adams: Thank you, Graeme, and good morning, everyone, and thank you for joining us. It was another exciting quarter for IAMGOLD with the first full quarters of operations at Cote, and another strong operating performance from Essakane and Westwood, putting us in a position to increase our overall guidance for the year. At a high level, I believe this quarter begins to paint a picture of what ultimately IMGOLD would look like. Cote Gold is now ramping up, providing for higher production base, lower cost profile, and shifting the density of our value to Canada. At steady run rate, Cote Gold will be among the largest gold mines in Canada and a model for mining -- for modern mining done right and for many decades to come. This is then coupled with strong and predictable productions in cash flow from Essakane and Westwood. In addition, as a company we are seeing our financial position growing stronger quarter-over-quarter, with the potential for significant step change in improvement next year when Cote is running at full steam and our prepaid commitments are behind us. This will position us with a clear roadmap for success, with strong free cash flow generations will be essential to ultimately deliver the balance sheet and drive value accretions for our shareholders. In next quarter, we continue to improve the business and get closer to our objectives. With that, we will now dive into the operating and financial results and highlights for the quarter. Starting with health and safety, IAMGOLD has continued to demonstrate a non-wavering commitment to safety accidents. At IAMGOLD, it is our priority to ensure everyone goes home safely. In the second quarter, our total recordable injury frequency rate was 0.6, an improvement from the prior quarter. I want to comment and congratulate the Essakane team, which recently surpassed the record health and safety milestone of 5 million hours work without recordable safety incident. Reaching [000] (ph) over such a period is a monumental achievement in our industry and a testament to the professionalism and commitment to a culture of safety of our people in Burkina Faso. Looking at operation, on an attributable basis, IAMGOLD produced 166,000 ounces of gold in the second quarter, bringing the year-to-date productions to 317,000 ounces of gold. As we will get into a moment, the second quarter production results were driven by Essakane being able to operate without disruption and benefiting from continued positive grade reconciliation. The continued ramp up of Westwood as the mine benefits from the rehabilitation of the underground and opening of new mining phases and of course the first quarter of production of Cote. The strong productions and sales volume translated to cash costs and all-in sustaining costs of $1,071 an ounce and $1,617 an ounce, respectively. Further, capital expenditure continued to step down quarter-over-quarter, totaling $119.7 million in the second quarter, as Cote transitions into operations and setting the stage for IAMGOLD to see growing free cash flow moving forward. Looking at our guidance, the strong first half positioned the company to beat on operating guidance for the year. Accordingly, we have increased our production guidance and lowered our cost estimate for the year. On production, IAMGOLD has increased its 2024 attributable gold production guidance for Essakane and Westwood to 495,000 to 440,000 ounces of gold, up from 430,000 to 490,000 ounces previously, as both of these mine has a strong first half of the year. At Cote, we are maintaining our guidance of 130,000 to 175,000 ounces on a 60% basis, but we now expect productions to come in the lower end of this range as improvements are made to mill availability. But we will get more into this in a moment as we walk through each asset. On operating costs, the 2024 cost guidance for Essakane and Westwood combined is now expected to be in the range of $1,175 to $1,275 per cash cost per pound sold. And $1,700 to $1,825 for AISC per ounce sold. This compared to the previous guidance estimate of cash cost per ounce sold of $1,280 to $1,400 and ASIC per ounce sold of $1,780 to $1,940. While we have brought our cost expectation lower this year, the updated guidance ranges are above our year-to-date performance as the increased guidance reflects the outperformance we saw in the first half and grades are expecting to come down at Essakane as we enter new mining phases. While inflationary pressures are easing, pricing for certain consumables including cyanide and grinding media remains in line with the levels experienced in 2023. With that, I will pass the call over to our CFO to walk us through our financial results and position. Maarten?

Maarten Theunissen: Thank you, Renaud, and good morning, everyone. In terms of our financial position, IAMGOLD ended the quarter with cash and cash equivalents of $511.4 million, and our credit facility remains undrawn, equating to total liquidity of approximately $915.7 million. We note that within cash and cash equivalents, $55.9 million was held by Cote Gold, and $188.2 million was held by Essakane. Essakane declared a dividend during the second quarter of $180 million for which the minority interest portion and withholding taxes were paid during the second quarter 2024. The net portion due to the Corporation of $151.9 million is expected to be paid by the end of this year. However, this is dependent on Essakane’s estimated future cash flow from operations to leave a sufficient working cash balance in country. Any unpaid amounts will be paid during 2025. We continue to see a risk on the ability to recoup all of the VAT receivables. Although the company was able to sell a small amount to a local bank in Burkina Faso during the second quarter. The company still has considerable obligations and factors which will influence our liquidity during the next 12 months. During May, the company completed a board deal equity financing for aggregate gross proceeds of approximately $300.2 million or $287.5 million net of fees. The company intends to use the proceeds from the financing to partially finance the repurchase of the 9.7% interest in Cota Gold from Sumitomo on November 30, 2024, with the difference funded from available liquidity. Additionally, the company has to deliver 150 ounces under its gold prepay arrangements from July 2024 to June 30, 2025. The prepay arrangements were funded at the time of entering into the arrangements. The company will receive some cash payments at the time of delivering into the gold prepay arrangements based on the amount that the market price of gold at the time of delivery as follows. For 50,000 ounces that will be delivered from July to December of this year, the company will receive the difference between the spot price and $1,700 per ounce, capped at $2,100 per ounce. For 31,250 ounces that will be delivered during the second quarter in 2025, the company will receive the difference between the spot price and 2,100 per ounce, capped at $2,925 per ounce. Lastly, the company expects to receive $84.4 million in gross proceeds in 2024 in respect of the closing of the remaining transactions arising from the remaining Bambouk asset sales. Please refer to the liquidity outlook section of the MD&A for further details. Looking at our Q2 financial results, high production resulted in lower unit costs as our operating costs remain in line with costs incurred during Q4 2023 and Q1 2024. With costs remaining in line with prior periods, the high realised gold price resulted in higher margins and higher free cash flow. Revenues from continuing operations totaled $385.3 million from sales of 167,000 ounces on a 100% basis at a record average realized price of $2,294 per ounce. The realized price includes the impact of the gold prepay arrangements delivered into during the quarter that reduced the realized price by $60 per ounce. The strong second quarter operating results coupled with the high gold price resulted in an adjusted EBITDA amount of $191.1 million compared to $152.5 million in the previous quarter of the year, which is $127 million higher than the $63.8 million adjusted EBITDA number in the second quarter of 2023. Adjusted earnings per share was $0.16 for the quarter compared to $0.11 cents in the previous quarter and a $0.01 cent loss in the second quarter of 2023. Looking at mine site free cash flow, which is calculated as cash flow from mine site operating activities, less capital expenditures from operating mine sites, Westwood and Essakane produced a recent high of $140 million, including Westwood, which returned its second quarter of positive mine site free cash flow since the restart after the June -- in June 2020, bringing its year to date title for the mine to $32.3 million. At Essakane, we note mine site free cash flow in the second quarter was $118.2 million, that is $81.8 million higher than the $36.4 million during the second quarter of 2023. And with that, I will pass the call back to Renaud. Thank you, Renaud.

Renaud Adams: Thank you, Maarten. We will walk through our operating performance at Essakane and Westwood before we dive into Cote. At Essakane, the mine reported attributable gold production of 111,000 ounces in the second quarter, up 26% from prior year periods and bringing the year-to-date total to 229,000 ounces. This was another very strong quarter of operation for Essakane and made possible by our mining operation being able to perform to plan in a quarter compound with continued higher than expected grades. Mining activities total 11 million tons in a quarter with only 2.2 million tons of ore mined as mining worked through a higher strip sequencing of the mine, coupled with limited mining in a part of Phase 6 due to localised instability which required enforcing and has been addressed since then. Head grade remain high at 1.46 grams a ton due to the continued positive reconciliations of grade from the reserve model as we continue to mine deeper into the Phase 5. This positive grade reconciliation in the deeper portions of Essakane was seen previously in Phase 5 and is continuing in Phase 4 and continuing in Phase 5. However, we are seeing head grades decline in line with the life of mine plan as volumes from Phases 6 and 7 increase and from increased proportion of stockpiles ore included in the mill fee. On a cost basis, Essakane reported second quarter cash cost of $1,081 per ounce and all-in sustaining costs of $1,481. The slight increase from the prior quarter went below our previous guidance due to strong productions and gold sales. With a strong first half of operations in 2024, Essakane production guidance has been revised upwards with attributable production expected to be in the range of 380,000 to 410,000 ounces. This compared to the prior guidance of 330,000 to 370,000 ounces of gold. The mill is expected to continue operating at nameplate capacity, though at average head grade slightly lower than in the first half of the year as per the mine plan. The cost guidance for Essakane has also been revised downward and is expected to be in the range of $1,175 to $1,275 for cash cost per ounce sold, and $1,575 to $1,675 for ASIC per ounce sold, approximately $100 to $125 per ounce improvement on both metrics due to the outperformance in the first half of the year. Capital expenditure guidance has been increased to approximately $175 million, primarily due to an increase in the strip ratio, not total tons mined, resulting in more mining costs being included in capitalized waste and equipment replacement. Essakane continue to be a significant cash flow contributor for IAMGOLD. With the current mine life through 2028, this operation has the capability to generate over a $1 billion of cash flow at current gold prices. We are continuing to examine the opportunities to extend the mine life of Essakane targeting options within [defence] (ph) to ensure the safety of our teams. Turning to Westwood, I want to congratulate the team on another improvement in the quarter. As the mine continues to test new highs and quarterly volumes from underground grades and production since the mine restarted in 2021. This improvement has meant that Westwood has generated, as Maarten noted, positive mine-free cash flow of nearly $22 million in the second quarter, bringing the year-to-date total to just over $32 million. On operation, Westwood produced 35,000 ounces in the quarter, a significant 84% over prior year period and bringing the year to date total to 67,000 ounces here today. Our mines from underground continue to step up and at a higher grade with 89,000 tons in the second quarter contributing to an average head grade from undergrown ore of 9.2 grams a ton. Mill throughput also increased in the quarter to 302,000 tons processed at an average blended head grade of 3.92 grams a ton and 92% recovery. The increase in throughput was driven by improved availability of 89% due to the ongoing maintenance program. The cost profile for Westwood continues to decline as operations improve. Cash cost averaged $1,131 an ounce and all-in sustaining cash averaged a promising $1,663 an ounce in the second quarter, continuing the trend of quarter-over-quarter cost improvement. Looking ahead, we have raised our guidance for this year, with Westwood now expected to produce between $115,000 to 130,000 ounces of gold at lower cash costs of $1,200 to $1,300 per ounce and ASIC of $1,775 to $1,900 per ounce. In the fourth quarter, we will be issuing an updated technical report and mine plan for Westwood, which will provide an updated mineral resource and reserve estimate and life of mine based on the last 2.5 years of mine optimizations efforts at Westwood. Turning to Cote Gold, we couldn't be more impressed with the work of our teams on the ground as they brought Cote to commercial productions only four months after the initial gold pour on March 31st, 24th, which was achieved within 90 days of first pre-commissioning activity. The ramp up of Cote has seen the project hit significant milestones in its first few steps as of mine. We took the path of testing first the capacity of the main equipment that drives the ultimate nameplate objective, and then build availability as we ramp up. From early on, the primary components of the processing circuits, primary and secondary crushing, HPGR, conveyors, ball mill, leaching, et cetera. All have proven their capability to operate on their design load when provided with stable conditions. During the same period, we also took the time to all of the team to stop and correct several deficiencies, as it is usually the case at early days of ramping up a large scale facility. The first week took about the whole first half of the second quarter, where 45 days go fast. In the second half of the quarter, efforts were made on slowly but surely cranking up the engine and testing the stability and the overall availability of the processing facility, while identifying all potential limiting factor to objective of exiting the year at 90% nameplate. In early July, the team pushed a commercial production button and reached our objective 30 days later, with nameplate production of 36,000 tons achieved on August 1st as the last day. On the dry side, we can report that we are very pleased with the performance of our HPGR and believe that it will bring great value down the road. During the ramp-up phase, we have identified some improvement required on the dry side in order to achieve design availability and performance. The first one has to do with mitigating the effect of abrasiveness on wear parts. The art Cote is highly abrasive, which was always known, but with actual effect to be experienced. Availability of the crushing and screening circuit in the second quarters was somewhat impacted by accelerating wear on the liners, feeders, and chute due to this abrasiveness. The new lining material has been identified and tested with good results in some critical area. Second, the continued core screening performance was also limited during ramp up. A new panel design are being proposed. Finally, dust management was challenging in the early days, and in particular, in the screening building. And while significant improvement has been made, more corrective action needs to be made. We have tested additions of suppressions, both water and surfactants, system in critical area with great results. So all in all, everything is solvable. We have identified corrective actions and we have initiated implementation of that. The company is planning a multi-day shutdown in September, at which time we will deploy key optimizations to address all of the issues and improve the long-term availability of the plant. We are very confident in the ability of Cote to ramp up well this year once we address these issues. Further, the power requirement of the plant has been lowered and unsuspended, providing important available capacity for down the road. In the second quarter, mining activities achieve a new high of 10.5 million tons of total material mined. Further, grade mined are continuing to come largely in line with our grade control block model in the current life of mine. Mining costs in the quarter, despite not yet running at full run rate, were comparable to Canadian open pit peers at just under the $4 a ton. An increase from the prior quarter due to temporary optimization activities on blasting patterns and production drilling, as well as some power curtailments experienced in June due to unseasonal heat wave. On processing, mill throughput in the second quarter was 834,000 tons at an average head grade of 1.4 grams a ton for a total of 34,000 ounces produced on a 100% basis. Revenue circuit would successfully commissioned toward the end of the quarter and recovery has responded well to the ramp up of the operations, averaging 90%. In July, Code Gold processed over 620,000 tons of ore with productions of nearly 26,000 ounces of gold. We have maintained our guidance at Code for this year, though we have guided to the lower end of the range of 220,000 to 290,000 ounces on a 100% basis. As improvements to mail availability are made during the ramp up of operations, reducing [indiscernible] prior to completing those solutions. We believe that exiting the year at nearly nameplate will set Cote and IAMGOLD for huge success starting early 2025. I will now hand the call back to Maarten for a brief update on projects ending this year.

Maarten Theunissen: Thank you, Renaud. I want to note that as we discuss project expenditures, all costs are being quoted on a 100% basis. Project and capital expenditures were $92.6 million in the second quarter and $288.9 million year-to-date. The expenditures include project expenditures of $30.7 million to support the completion of commissioning and certain scopes of non-critical path earthwork and infrastructure. Prior to the first goal pour on March 31, project expenditures were $151.7 million, totaling $182.4 million for the year. $24.5 million of operating expenditures related to milling and surface costs have been capitalized in the second quarter and $51.5 million year-to-date in support of the commissioning and ramp up efforts in advance of achieving commercial production. Capital expenditures related to operations for the second quarter were $37.4 million and $55 million year to date. Capitalized waste stripping and capitalized operating costs are expected to be higher when compared to guidance, which is offset by lower capital related to operations due to some of the equipment being purchased through our increased leasing facility. The total of all of our capital expenditures of $454 million, as well as the timing of the expenditures, are in line with the forecast and guidance for the year. Back to you, Renaud.

Renaud Adams: Thank you, Maarten. So that is that. Our goal this year is very clear. We need to ramp up the plan availability and utilization to exit the year at a throughput rate of approximately 90% of nameplate and start 2025 on a very strong footing. This brings us to the slide we always like to finish on and this is what the future is for Cote. We are continuing to advance in our understanding of the impact of Gosselin and potential of the project. At year end of 2023, we updated the Gosselin mineral reserve and resources estimate with an additional 35,000 meters of drilling, which was drilled over the two years prior. This year itself, we are conducting a 35,000 metre drill program targeting the central zone between the pit shells where we see indication of continuation of mineralization and hydrothermal breccias, as well as some deeper holes to understand the continuity of the mineralization below the current pit shelf. When we look at the resource and reserve statement, the Code deposit has estimated mineral reserve on a 100% basis of 7.6 million ounces. These reserves form the basis of the current economics of the project. On a measured and indicated resource basis, the Code pit is currently estimated at a total of 12.1 million ounces. The adjacent Gosselin pit has an additional 4.4 million ounces of measured and indicated resources and nearly 3 million ounces of inferred, bringing the project to a total of 16.5 million ounces of measured and indicated and an additional 4 million ounces of inferred. The size of Code and Gosselin together put the project and the mine in a very exclusive company amount large-scale producing Canadian assets. We expect to have the result of this program later this year, which will greatly inform our understanding of how to incorporate Gosselin and remaining measured and indicated into a potential future of my plan. So, thank you all, and I look forward to a very exciting year ahead. With that, I would like to pass the call back to the operator for the Q&A. Operator?

Operator: Thank you. We'll now begin the question-and-answer session. [Operator Instructions] The first question comes from Anita Soni with CNBC World Markets. Please go ahead.

Anita Soni: Good morning, Renaud, everyone. My first question is with respect to Cote. What factors are -- what are the main factors that drove the indication that you're going to be near the bottom end of the production guidance range at Cote. Is it throughput rate, recovery rate? And then the second one probably relates to that. How long will that shutdown last in September?

Renaud Adams: Thanks for your questions. And as you're also the one that asked me early in the year how we set the original guidance. I would say that it's mostly a matter of the total tons milled. So if you recall, we set the guidance early in the year of 220,000 to 290,000, specifying that we were confident in the high grade, which is happening, but also basically saying that at a perfect commissioning without any need for further downtime and so far with a 6.5 million ton process or so, we'll set the 290,000. As I explained in my comments, we really did take the time in Q2 to properly stop and correct things as we move forward. This has been our philosophy since day one and I'm very pleased in its pain, maybe a little pain in the short term on the total ounces, but we're definitely going to shift the profile starting in 2025. So we did that in Q2 and as I mentioned, so to your point is, originally speaking, we were probably thinking of five days in September, but we're prepared to go further. So, if it takes additional downtime, another five, seven days for total of 10, 15, whatever it takes to correct all those issues. If it takes less, we may perform better than the lower end, but we just want to make sure that we're prepared to take the time and set [indiscernible]. So let's call for a 10 to 15 max and we'll see how it goes for the remaining [indiscernible]. So largely the time process and as we correct things as we move forward.

Anita Soni: Okay. Thank you. And then I noticed you provided mining costs per ton for the Q2. Thank you for that. I know -- and I also know that relatively short period of time since you've declared commercial production on August 7th, but can you give us an indication how the processing costs are going at this stage?

Renaud Adams: Maarten?

Maarten Theunissen: Good morning, Anita. The processing cost on a total basis is actually well within our expectation and our plans. There is, of course, some additional costs being incurred as they are fixing or replacing certain things. But when we look at where we are, we expect the dollar per tonne cost when we get to the end of the year to be in the ranges that we guided and disclosed previously. So in line with the 43-101 with slight increases because of inflation, but also just we won't be at a 100% yet, but our expectation on the cost of the mill have not reduced, or have not changed at this point.

Renaud Adams: I think Maarten, it's fair to say that, the range of the 10 to 15 is just a matter of the tons milled. So we were still low -- globally low, with 839,000 tonnes milled in the second quarter, but with only one month of 620,000, so we're expecting to get closer to the 10 to 11 objective as we exit the year, but it's really a matter of time.

Anita Soni: And that power, as you mentioned, that you're using less power or is that factoring into that lower benefit on cost?

Renaud Adams: Yes, but also power, even though it's a massive, it's a big operation. Power cost per kilowatt would be extremely low at Cote as we manage fees and we're expecting one of the lowest cost per kilowatt pretty much in the industry. So, yes, this is, but the real benefit beyond potentially saving is the opportunity of using this extra power down the road. As we well-documented, there's some -- like the 72 megawatts, so you use it how you want, right? And this is what we're the most excited about is, we feel that the main equipment on the wet side may drive more tons down the road. That's the nameplate.

Maarten Theunissen: It has to be proven on a steady basis, but what we've seen so far is we're definitely using less power for the same throughput.

Anita Soni: And then just an idea of -- in terms of the build out in the summer time, I noticed the mining rates on ore were similar to last quarter. So I'm just assuming you guys are a little bit more focused on building the tailings dam over the summer months. Is that correct? And when -- how much -- how many tons do you have to deliver to the tailings dam in Q3?

Renaud Adams: I don't have the details of the tons, but if you recall, and as described as well in the 43-101, so we're basically executing the whole Phase 2, right? And this will -- combined with the fact of the throughput, the ramp up will position towards the 18 months of capacity. And then [indiscernible] summer will add. But yes, we're completing the Phase 2 that we've initiated last year. We're completing it this year. And then by far, we should have minimum of 18 months ahead of us, and then we'll continue on the yearly basis to raise. And our objective is to be comfortably sitting at least under 24 months beyond.

Anita Soni: Okay. And my last question, just in terms of stockpile levels, can you tell us how many tons of ore you have stockpiled ahead of the mill right now and what the average grade is there?

Renaud Adams: Bruno, you got this?

Bruno Lemelin: Yes. Good morning, Anita. So, so far we have 8 million tons grading at 0.75. We have different categories of stockpiles with direct feed high grade ore and low grade ore. So, so far we are pretty satisfied with the level of stockpile and also with the reconciliation on the high grade category.

Anita Soni: And then you mentioned I think that you are directing more higher grade from the pit to the mill, what would that high grade be on average?

Bruno Lemelin: We define high grade whatever is above the 0.7, 0.8 gram per ton category. So right now we have a good -- fair amount of stockpile at 1.6 gram per ton in front of us. And we have also some run of ore mine at 1.14.

Renaud Adams: We'll try to keep the mill towards the 1.5 till the end of the year. We did very well in July as well. So there is no issues or reason to believe we won't deliver the grade. So it's really about cranking up the tonnage or throughput, but the mine has been doing very well so far.

Anita Soni: Okay, thank you. That's it for my questions and congratulations on hitting commercial production.

Renaud Adams: Thank you so much.

Operator: The next question is from Wayne Lam with RBC. Please go ahead.

Wayne Lam: Thanks, guys. Good morning, everyone. I'm just wondering, maybe at Cote, if you might be able to speak to the performance of the autonomous operations date and the haulage and drilling, just where the challenges have been and how you've mitigated those risks?

Bruno Lemelin: I wouldn't call too many risks to be mitigated. I think more -- every quarter that goes by, we get more comfortable with autonomous college and it has been operating very well and Renaud just mentioned the stockpile and everything that's been processed. So basically every single ton that has been put on the stockpile has been with autonomous trucks. And it's been performing extremely well at a very high availability and so forth. So I honestly do not see any issues with them and hopefully over time we could be even better and with our drilling automation as well. So working hard on both, but autonomous is absolutely working beautifully and not to underestimate as well the health and safety aspect of not having operators behind the steering. It's not about cutting job, it's really about improving, modernizing our operations and make it safer. But so far so good, excellent. I'll give a very high score to the implementation of autonomous college. I will redo it anytime.

Wayne Lam: Great. It sounds like things are going pretty well. Maybe moving to Westwood, just on the grades there which seem pretty positive relative to the reserve. Do you see those grades continuing through the year? And then with the upcoming technical report, do you see upside to the targeted run rate from the underground beyond the 900 tons per day? And given the strong performance of the mine now with the underground now rehabilitated, do you envision that asset as one to keep in the portfolio longer term or could it potentially be classified more as non-core?

Renaud Adams: I’ll go in other. My KPI is in every quarter I've seen the asset ramping up with more tons from underground, the overall grade improving from underground. We're sitting on a reserve of roughly 10, 10.4 grams a ton reserve. And that's the ultimate objective. You need to position yourself at some point where you start mining at the reserve grade at Westwood and this is where you're going to feel that you have reached a certain stability and sustainable. So pretty close too. We could be basically one quarter away of reaching. Once you get that, you want like I said, to continue to operate along these lines. We're extremely, extremely pleased to how Westwood has performed and continue to perform in the cash flow. So comfortable to say that at this stage, we're very pleased with both Essakane and Westwood. And we definitely can see these two minds continue being a big collaborator, if you will, to our -- contributor to our story. Having said that, I don't think so we've seen the end of the optimization of Westwood. So we're going to put the 42-101. We want to see what we could do, where we could get. And as I said, strong production profile and improving and free cash flow. So we're very, very pleased. On the total tons, we see Bruno getting wet a bit here. So what do you see down the road?

Bruno Lemelin: Thank you, Renaud. Actually the performance from underground is getting better and better due to the [indiscernible] work we've done over the last two year and a half. It's proved to be very beneficial for us in our ability to reach our targets at 900 tons per day. Of course, we have vision to increase this closer to the 1,100. Those are the kind of targets we're looking at. Again with the new 43-101 we'll be able to express with more clarity what those targets are going to be and also the extent of the life of mine with the new block model. So at that time we'll be able to give more insight related to that mining plan.

Wayne Lam: Okay, great. Thanks. And then maybe just last one, just on the Bambouk assets, can you provide a bit more clarity on the final payment and whether there's any credit risk associated with that? Just seems like it's been a bit delayed and wondering what the risk is to that final payment coming in.

Renaud Adams: Yes, it's a fair comment that it's been a bit long and I can assure you it's been a bit long for us as well. But I think we're making great progress, honestly. So we're still comfortable of the closing of Guinea in the second half. And following that, we'll address another closing in Mali. So can we close both? No, we're still saying that. We're still saying that they're both, were working towards closing both remaining, talking about roughly 80 million of growth proceeds for both. So it's meaningful, it's important. It's important for people as well, because as you mentioned, we've got to move on here and allow everyone to move on. So we're very active and remain confident we're going to close both this year.

Wayne Lam: Okay, great. Thanks for taking my questions.

Operator: The next question is from Mike Parkin with National Bank Financial. Please go ahead.

Mike Parkin: Hi, guys. Congrats on the solid quarter. Most of my questions have been answered. Just a couple of follow-ups. You gave us good color on expected shutdowns at Cote. Can you give us any guidance around shutdowns planned at Westwood or Essakane?

Renaud Adams: Definitely nothing extraordinary beyond the regular. So you're looking at the average availability of Essakane and Westwood. We achieve 89%, so I think it's fair to think that we're going to try to maintain around that level to the end of the year. And this is basically done through plant shutdown, a little bit of on plan, but we don't have anything struggling. And I think the same comment goes for Essakane as well. There's always, of course, things to be addressed, but we're not planning beyond the regular availability. So both mine should be in the availability or better of what you've seen in Q2.

Mike Parkin: Okay. And then the target at Cote to be at 90% of nameplate by year end, is that -- like, obviously you put out a daily number just recently and it's well on it, it's at nameplate. But what's the 90% based on? Is that like a trailing four-week average?

Renaud Adams: I'll be very, very happy by accumulating four weeks. Let's say if what we've done in commercial using 50% of nameplate if we repeat that in December and we feel very strong this is what we call exiting the year. So thanks for asking, but internally this is how we would feel. It's not about a few days. We know we've done it one day. We know it's capable to be done. But as you ramp up, you want to make sure that you're solidly on the saddle and comfortably sitting on the saddle by the end of December. So let's call 30 days, averaging 90 percent will be our key objective in December.

Mike Parkin: Great, that's it from me, guys.

Renaud Adams: Thanks.

Operator: The next question is from Carey MacRury with Canaccord Genuity. Please go ahead.

Carey MacRury: Hi, good morning. Just a follow-up on the mill throughput. Obviously, you've hit commercial production. Should we be assuming that the mill is kind of going to run at around 60% through August up until the shutdown or is the mill performing a bit better than that now?

Renaud Adams: No, definitely from the moment you hit the 60%. I would exclude September, because like I said, September is the big month where we're going to be making a lot. But yes, if 60% has been reached and becomes the baseline now. So from that point on, we need to continue to improve. August, September will be for the time of fixing, but definitely it's some kind of a steady ramp up with a little bit of a dip in September allowing for the shutdown, but 60% is and will remain the new baseline.

Carey MacRury: Okay. And then just maybe a question for Maarten on the Sumitomo buyback, I see the option there is, I think $380 million, given the ramp up, is that more or less where it's going to be or do you expect that to move around plus or minus?

Maarten Theunissen: Good morning, Carey. We don't expect that number to change significantly, but it is dependent on the August cost and the August sales, because that still gets the July and August cost and sales, because that still gets incorporated into that and the gold price has an impact, but we don't expect it to change materially from the $380 million expected previously as well.

Carey MacRury: Great. That's it for me. Thanks.

Operator: The next question is from Steven Green with TD Securities. Please go ahead.

Steven Green: Good morning, everyone. Just a quick accounting question for you. Up until now you've been capitalizing your interest on Cote. Can we expect that will all start being expensed after the August 2nd date?

Maarten Theunissen: Yes, we will start depreciating the asset and we will stop capitalizing of our end cost after achieving commercial production, which we -- it would be either beginning August or beginning September, but probably beginning August.

Steven Green: Okay, great. That's all I have.

Operator: [Operator Instructions] The next question is from Tanya Jakusconek with Scotia Bank. Please go ahead.

Tanya Jakusconek: Great. Good morning. Thank you very much for taking my questions and congrats on getting Cote commercial. I just wanted to come back, I know a lot of questions have been asked, I needed it quite a bit on that, starting off on Cote. Can I just go back to starting on the -- just on the pit you said the grade meets the block model, just remind me right now on the availability of your truck, what are they operating at availability-wise?

Renaud Adams: We're definitely on the specs, so 85% -- just confirm, 85% or so. So this is how you want to see a [indiscernible].

Tanya Jakusconek: Okay. And then can I ask just looking at some -- so going back to the processing facility -- oh sorry, before the processing facility, just the stockpiles? You gave us the 8 million tons for the 0.75. Can you just give me what the stockpile tonnages for the 1.6 grams per ton? Because I know that's what you're going to be feeding in the short term through the processing facility. So what do we have in 1.6 grams per ton?

Bruno Lemelin: Hello, Tanya. We're talking about [half a] (ph) million tons right now, and we have packets in front of us directly in the pit.

Renaud Adams: We use a bit of stockpile of course during the ramp up and the mine was getting new facing prepared and so forth. So we've entered now much like good grades and long and continuous benching. So expecting pretty good grades till the end of the year.

Tanya Jakusconek: End of the year. Yes, and you mentioned the 1.4. Okay, perfect. And then as we…

Renaud Adams: Yes, we did 1.4. Sorry, just to clarify. So we did 1.4 in Q2, but now that we're primed, if you will, so we'll like to maintain more towards the 1.5 through the end of the year.

Tanya Jakusconek: Okay. So you are going to take a bit more of that higher grade stock file through as well?

Renaud Adams: No, we just -- well, maybe, but also the mine will be producing more until the end of the year of that higher grade.

Tanya Jakusconek: Okay, that's helpful. And then as we get into the processing facility and we're down for that 10 to 15 days, just wanted to make sure like -- you're tacking the liners on the screens. Do we have all of this inventory on site right now or are we still having to purchase or have this come to site?

Renaud Adams: A lot of that already, Tanya, the some will come later on in August, some of the latest will be kind of very early September. So we feel that we're going to be fully equipped to address all those issues. So we're not expecting any issues on [indiscernible].

Tanya Jakusconek: Okay. And then just on the dust that you talked about, was that just -- a lot of dust that you're having to fight against the permit, or what was it about the dust in general that you needed to -- I understand you need to control dust, but I'm just wondering if it was a permit or if it was just a normal operating dust issue.

Renaud Adams: I would say more operating things. I mean, like, the objective is very clear. You visited a lot of assets and know what it is. And in the screening building and the crushing building, using a mask should be a second layer of protection and not the main layer. So that's the bar. It's like our commitment to health and safety, rules are very strict as well of course in Ontario as it should be. So we're going to bring this to basically the zero, the zero dust fugitive and dust and so forth. So we were not there at the beginning, of course, a lot of adjustment but as we advance in August we have some sectors now that really look like zero dust. So this is basically what has to do. So most likely we're just going to extend to every single critical area, the suppression system. We're working with the manufacturer as well to make the dust collecting system more efficient as well, more -- and some optimization. So the combinations of both were very, very confident that we'll solve the problem once [indiscernible] September.

Tanya Jakusconek: Okay. And just on the processing costs that were quoted, the $10 to $15 a ton, I just want to make sure that's USD?

Maarten Theunissen: Yes.

Tanya Jakusconek: Okay. And then -- thank you for that. All my questions on, and congrats on getting this up. It looks like it's coming along nicely. Can I just move to my final question, which is just on the guidance for the remaining portion of the year for the company as a whole, we do have the lower grades coming in at Essakane? Is that coming in like slowly, i.e. Q3 is lower than Q2 and then a lower Q4? Or are we already in the low grade and it's sort of even in the two quarters.

Renaud Adams: Yes, the first part, like July was somewhat like a transitions and remain good. And I think, from there, like as we enter August, like slowly we see this ramping down, but it wasn't like a dry cut at the end of Q2. So we had a good July and we continue and now we're transitioning slowly. And on that, I know when you're looking at the guidance, as I mentioned, it looks like we're performing better the year-to-date and how we look at Essakane as well as we set the guidance, there is some sort of risk adjusted effect as well there. So we all understand the situations and it would take only a month of interruptions of supply or LFO being used for power, so there's a bit of a risk adjustment and just like happened in the first half, if the second half is very stable, you have no disruptions and the mine operates according to his plan, there is no reason to believe that we will not perform extremely well under those new updated guidance.

Tanya Jakusconek: Okay, so looks like Q3 a bit lower and then Q4 will be the lowest. And then for Westwood with the revised numbers, are we still looking at quarter-over-quarter improvement, Q3 over -- and then better improvement in Q4 on the grade side.

Renaud Adams: Yeah, but as I mentioned, we're almost now already at the reserve grade, right? So there would be a point where you don't want to [indiscernible] So you're going to be following. So we're almost there. So if everything goes as well, well Fayolle is over. So there's about 10,000 ounces of the first half of the year that came from Fayolle. So this one is -- so we had a very good -- a very good grade in the Grand Duc as well in kind of the second half of Phase 1. So that's also. So all those elements will maybe not be there in a second. So when you're looking at, I think the underground will continue to improve, but you may lose a bit of grade towards the Grand Duc, and you won't benefit the answers from Fayolle. So could we repeat H1 and H2? A little more challenging, but if the mine continues to ramp up well on the ground, we could be well positioned as well under this new guidance.

Tanya Jakusconek: Okay. It kind of looks like you're almost there on grade, so mainly evenly distributed for the second half. Okay. Thank you so much for taking all my questions. I really appreciate it, and congrats again.

Renaud Adams: Thank you so much.

Operator: This concludes the time allocated for questions on today's call. I'd now like to hand the call back over to Graeme Jennings for closing remarks.

Graeme Jennings: Thank you very much, operator. Thanks to everyone for joining us this morning. As always, should you have any additional questions, please reach out to Renaud or myself. Thank you all, be safe and have a great day.

Operator: This brings to a close today's conference call. You may disconnect your lines. Thank you for participating and have a pleasant day.

This article was generated with the support of AI and reviewed by an editor. For more information see our T&C.

Latest comments

Risk Disclosure: Trading in financial instruments and/or cryptocurrencies involves high risks including the risk of losing some, or all, of your investment amount, and may not be suitable for all investors. Prices of cryptocurrencies are extremely volatile and may be affected by external factors such as financial, regulatory or political events. Trading on margin increases the financial risks.
Before deciding to trade in financial instrument or cryptocurrencies you should be fully informed of the risks and costs associated with trading the financial markets, carefully consider your investment objectives, level of experience, and risk appetite, and seek professional advice where needed.
Fusion Media would like to remind you that the data contained in this website is not necessarily real-time nor accurate. The data and prices on the website are not necessarily provided by any market or exchange, but may be provided by market makers, and so prices may not be accurate and may differ from the actual price at any given market, meaning prices are indicative and not appropriate for trading purposes. Fusion Media and any provider of the data contained in this website will not accept liability for any loss or damage as a result of your trading, or your reliance on the information contained within this website.
It is prohibited to use, store, reproduce, display, modify, transmit or distribute the data contained in this website without the explicit prior written permission of Fusion Media and/or the data provider. All intellectual property rights are reserved by the providers and/or the exchange providing the data contained in this website.
Fusion Media may be compensated by the advertisers that appear on the website, based on your interaction with the advertisements or advertisers.
© 2007-2024 - Fusion Media Limited. All Rights Reserved.