Power auction casts doubt on extra capacity plans

Published 09/12/2016, 10:55
© Reuters. Autumn mists sit behind electrical pylons on the river Tummel near Pitlochry in Scotland
BARC
-
EDF
-
CNA
-
SSE
-
NG
-

By Nina Chestney and Susanna Twidale

LONDON (Reuters) - Prices in Britain's latest auction for back-up electricity came in well below expectations, casting doubt on how much extra capacity utilities will commit to building to ensure the country avoids winter supply shortages.

Thursday's auction for 2020/21 supply cleared at 22.50 pounds per kilowatt (kW)/year, while analysts have said a price of 35-45 pounds was needed to spur new gas plant investment.

Britain began capacity auctions in 2014, looking to head off future power shortages as coal plants close and as low electricity prices dissuade investors from building new capacity.

Plant owners are paid to make available back-up power at short notice.

Utilities Centrica (LON:CNA), SSE (LON:SSE), Drax, EDF (PA:EDF) Energy, RWE, E.ON, Scottish Power and Uniper were among 166 applicants provisionally awarded capacity agreements.

Contracts for 52.43 gigawatts (GW) of electricity were awarded in the auction on Thursday.

"5.8 GW of existing capacity exited the auction above the clearing price and is now at increased risk of financial closure as a result in our view," analysts at Barclays (LON:BARC) wrote.

"Notable plants to miss out on capacity payments include SSE’s Peterhead and Fiddler’s Ferry stations... and (on first look) Drax's new (gas) projects – with the company having previously stated that they would hold back these projects until the auction cleared at a sufficiently high price," they wrote.

There are concerns Britain may face electricity supply shortages over the next few winters as coal plants close. The government has said it wants to have up to 26 GW of new gas generation built by 2030.

"It appears that the only successful 'new' large (gas) projects were extensions or significant refurbishments of existing sites – thereby reducing investment cost requirements," the Barclays analysts wrote.

'NEW GENERATION'

The government said the auction had brought forward a range of new generation, including Centrica's 370-MW gas-fired plant in King's Lynn and InterGen's 300-MW extension to its gas plant in Spalding.

SSE said it had secured agreements to provide 3,239 MW of 2020/21 capacity but its Peterhead gas plant and Fiddler's Ferry coal plant were not awarded agreements.

It said the auction results would not affect its operational stations, which would be available this winter.

Drax secured contracts to provide 1.2 GW of capacity from existing units. On Tuesday it said planned to buy four open-cycle gas turbine plants with a capacity of 1.2 GW but these did not secure agreements.

"Our plans remain unchanged – the acquisition of the four rapid response OCGT projects is a long-term investment," a Drax spokesman said.

Britain's National Grid (LON:NG), which operates the 2-GW Interconnexion France-Angleterre (IFA) power link with French grid operator RTE, won a contract for almost 1.2 GW.

© Reuters. Autumn mists sit behind electrical pylons on the river Tummel near Pitlochry in Scotland

National Grid said the auction results would remain provisional until confirmation by Britain's secretary of state for energy on Dec. 20.

Latest comments

Risk Disclosure: Trading in financial instruments and/or cryptocurrencies involves high risks including the risk of losing some, or all, of your investment amount, and may not be suitable for all investors. Prices of cryptocurrencies are extremely volatile and may be affected by external factors such as financial, regulatory or political events. Trading on margin increases the financial risks.
Before deciding to trade in financial instrument or cryptocurrencies you should be fully informed of the risks and costs associated with trading the financial markets, carefully consider your investment objectives, level of experience, and risk appetite, and seek professional advice where needed.
Fusion Media would like to remind you that the data contained in this website is not necessarily real-time nor accurate. The data and prices on the website are not necessarily provided by any market or exchange, but may be provided by market makers, and so prices may not be accurate and may differ from the actual price at any given market, meaning prices are indicative and not appropriate for trading purposes. Fusion Media and any provider of the data contained in this website will not accept liability for any loss or damage as a result of your trading, or your reliance on the information contained within this website.
It is prohibited to use, store, reproduce, display, modify, transmit or distribute the data contained in this website without the explicit prior written permission of Fusion Media and/or the data provider. All intellectual property rights are reserved by the providers and/or the exchange providing the data contained in this website.
Fusion Media may be compensated by the advertisers that appear on the website, based on your interaction with the advertisements or advertisers.
© 2007-2024 - Fusion Media Limited. All Rights Reserved.