Shell delays U.S. Lake Charles LNG export project to 2025

Published 04/09/2019, 12:52
Updated 04/09/2019, 12:56
Shell delays U.S. Lake Charles LNG export project to 2025
SHEL
-
NG
-
ET
-

LONDON (Reuters) - Royal Dutch Shell (L:RDSa), one of the world's largest liquefied natural gas (LNG) suppliers, has asked U.S. regulators to extend the time by which it should complete an LNG export project in Louisiana by five years to 2025, regulatory filings showed.

The project, a 50-50 venture with U.S. midstream company Energy Transfer (N:ET), envisaged converting an existing import and regasification facility in Lake Charles into a multi-train, 16.45 million tonnes per year (mtpa) facility.

The delay takes a major U.S. export project out of the race to achieve a final investment decision (FID) in time to start operations during an anticipated supply downturn in 2023-2024.

About a dozen projects in North America, mostly in the Gulf of Mexico, are vying for FID this year or early next year to start production in time to hit that sweetspot. But the more get approved, the less likely other projects are to go ahead as the expected dearth turns into oversupply.

The delay is due to Shell's takeover of the project after its $53 billion (£43 billion) acquisition of BG Group in 2016 prompted it to re-evaluate and strike new agreements, the Anglo-Dutch company said in a letter dated last Friday to the Federal Energy Regulatory Commission.

It said following this process, the project plans had not changed but a new 50-50 ownership structure with Energy Transfer had been struck and Shell had committed to taking 50% of the export capacity.

"Under the new Project Framework Agreement, ET and Shell have established a detailed process for the development of the Project which includes milestones that are expected to result in the Project sponsors reaching FID as early as the end of 2020," it said in the letter.

"Completion of construction of the LNG export terminal facility is expected to occur as early as the second half of 2025."

Latest comments

Risk Disclosure: Trading in financial instruments and/or cryptocurrencies involves high risks including the risk of losing some, or all, of your investment amount, and may not be suitable for all investors. Prices of cryptocurrencies are extremely volatile and may be affected by external factors such as financial, regulatory or political events. Trading on margin increases the financial risks.
Before deciding to trade in financial instrument or cryptocurrencies you should be fully informed of the risks and costs associated with trading the financial markets, carefully consider your investment objectives, level of experience, and risk appetite, and seek professional advice where needed.
Fusion Media would like to remind you that the data contained in this website is not necessarily real-time nor accurate. The data and prices on the website are not necessarily provided by any market or exchange, but may be provided by market makers, and so prices may not be accurate and may differ from the actual price at any given market, meaning prices are indicative and not appropriate for trading purposes. Fusion Media and any provider of the data contained in this website will not accept liability for any loss or damage as a result of your trading, or your reliance on the information contained within this website.
It is prohibited to use, store, reproduce, display, modify, transmit or distribute the data contained in this website without the explicit prior written permission of Fusion Media and/or the data provider. All intellectual property rights are reserved by the providers and/or the exchange providing the data contained in this website.
Fusion Media may be compensated by the advertisers that appear on the website, based on your interaction with the advertisements or advertisers.
© 2007-2024 - Fusion Media Limited. All Rights Reserved.