Westinghouse wins UK reactor approval from nuclear regulator

Published 30/03/2017, 13:48
© Reuters. FILE PHOTO: The logo of the American company Westinghouse is pictured at the World Nuclear Exhibition 2014 in Le Bourget
EDF
-
ENGIE
-
6502
-

By Susanna Twidale and Nina Chestney

LONDON (Reuters) - Toshiba's  (T:6502) Westinghouse, which filed for bankruptcy on Wednesday, has won approval for its AP1000 reactor design, Britain's nuclear regulator said on Thursday.

The Office for Nuclear Regulation (ONR) approval is needed before the design can be used at NuGeneration Ltd's (NuGen) Moorside new nuclear project in north west England, which consists of three AP1000 units.

"The closure of our assessment of the generic design of the AP1000 reactor is a significant step in the process, ensuring the design meets the very high standards of safety we expect," Richard Savage, ONR's chief nuclear inspector, said.

"We will now focus our regulatory attention on site specific assessments, and NuGen's application for a nuclear site licence," he added in a statement.

Westinghouse's bankruptcy filing has raised questions over whether it will be able to complete capital intensive projects, although the move does not affect Westinghouse's operations in Asia, Europe, the Middle East and Africa, according to a company statement.

All new nuclear plants in Britain need ONR approval through its GDA process, which typically takes around four years and the Westinghouse reactor was expected to be approved by the end of this month.

The approval has taken much longer since assessment first began in 2007. It was paused by the ONR at the end of December 2011 while it asked for design modifications, but was resumed in 2014.

"(The regulator review) represents a major milestone towards bringing a new generation of safe, clean energy to the United Kingdom through the Moorside Project,” José Emeterio Gutiérrez, Westinghouse interim president and chief executive, said in a statement.

"In addition, it expands the global regulatory pedigree of the AP1000 plant design and further confirms Westinghouse’s innovative safety technology," he added.

Britain needs to invest in new infrastructure to replace ageing coal and nuclear plants set to close in the next decade, but has struggled to get large projects built, especially nuclear, due to the costs involved.

EDF's (PA:EDF) 18 billion pound ($22.5 billion) Hinkley Point C nuclear project in southwest England got the final go-ahead in 2016 after several years of delay, but only after securing backing from the French government.

NuGen, a joint venture between Toshiba and French utility Engie (PA:ENGIE) has also come under doubt since Japan's Toshiba said last month it planned to pull out of the construction work at the British plant after posting a $6.3 billion writedown on Westinghouse, which has been hit by billions of dollars in cost overruns at new nuclear plants.

© Reuters. FILE PHOTO: The logo of the American company Westinghouse is pictured at the World Nuclear Exhibition 2014 in Le Bourget

A spokesman for NuGen said it could not comment on specific financial issues relating directly to Toshiba or Westinghouse and that it will continue "business as usual" to gain the necessary permits and licenses to build the project.

(additional reporting by Karolin Schaps; editing by Alexander Smith)

Latest comments

Risk Disclosure: Trading in financial instruments and/or cryptocurrencies involves high risks including the risk of losing some, or all, of your investment amount, and may not be suitable for all investors. Prices of cryptocurrencies are extremely volatile and may be affected by external factors such as financial, regulatory or political events. Trading on margin increases the financial risks.
Before deciding to trade in financial instrument or cryptocurrencies you should be fully informed of the risks and costs associated with trading the financial markets, carefully consider your investment objectives, level of experience, and risk appetite, and seek professional advice where needed.
Fusion Media would like to remind you that the data contained in this website is not necessarily real-time nor accurate. The data and prices on the website are not necessarily provided by any market or exchange, but may be provided by market makers, and so prices may not be accurate and may differ from the actual price at any given market, meaning prices are indicative and not appropriate for trading purposes. Fusion Media and any provider of the data contained in this website will not accept liability for any loss or damage as a result of your trading, or your reliance on the information contained within this website.
It is prohibited to use, store, reproduce, display, modify, transmit or distribute the data contained in this website without the explicit prior written permission of Fusion Media and/or the data provider. All intellectual property rights are reserved by the providers and/or the exchange providing the data contained in this website.
Fusion Media may be compensated by the advertisers that appear on the website, based on your interaction with the advertisements or advertisers.
© 2007-2024 - Fusion Media Limited. All Rights Reserved.